The purchase of rail passenger rolling stock to operate the regional connection
on the line of Warsaw Commuter Rail in the Warsaw Metropolitan Area
Get more information

Implementation schedule

  • 11.05.2009: announcing tender procedure for the purchase of 14 pcs. of new electric traction units for WCR
  • 01.19.2010: settlement f tender procedure for the purchase of  14 pcs. of new electric traction units for WCR
  • 03.26.2010: signing the agreement between Warsaw Commuter Rail and Pojazdy Szynowe PESA Bydgoszcz S.A.
  • 02.15.2011: entering the project of WCR – by the decision of the Management of Mazovian Voivodeship – on the basic list of Indicative List of Individual Key Projects of RPO WM
  • 05.04.2011: signing the pre-agreement with the Managing Institution of ROP Mazovia – represented by the Management of Mazovian Voivodeship
  • 12.07.2011: delivery of the first vehicle of EN97-001 for the locomotive depo in Grodzisk Mazowiecki
  • 12.30.2011: filing the application on subsidy for the WCR project with the Mazovian Unit of Implementing European Programmes
  • 01.11.2012: final receipt of the first vehicle by WCR
  • 01.12.2012: launch of monitored exploitation of the vehicle EN97-001 in passenger traffic
  • 02.17.2012: launch of regular service of WCR line by the vehicle EN97–001 under the timetable in force
  • 03.30.2012: receipt of the second the supplied vehicle and starting consecutive deliveries
  • 07.12.2012: signing the agreement on subsidy for the WCR project
  • 09.30.2012: finishing deliveries of new vehicles
  • 01.01.2013: launching the operational stage of the Project